WP3 — Benchmark Validation & XAI

Lead: Joint — ITU + SJU
Timeline: M10 – M22
Key milestone: M16 — First Q1 paper submitted; M22 — Second Q1 paper submitted

Objectives

  1. Cross-validate PI-VIB-ResNet on Oxford, NASA, and T-EV datasets
  2. Compare against ≥5 state-of-the-art baselines
  3. Apply SHAP and gradient saliency for explainability
  4. Publish ≥2 Q1 journal papers

Comparison Matrix

ModelDatasetRMSEStatus
SVROxfordTBDPlanned
LSTMOxfordTBDPlanned
TransformerOxfordTBDPlanned
AE-BPNNAll~1.8%Published
PI-VIB-ResNetAll≤1.2%KTBIX Target

Deliverables

  • D3.1: Benchmark comparison report (M18)
  • D3.2: SHAP analysis report (M20)
  • P1: Q1 journal paper — PI-VIB-ResNet architecture (submitted M16)
  • P2: Q1 journal paper — XAI for second-life batteries (submitted M22)